Electrical Subcontractor Wins 100% of Unpaid Certified Claim

A Kedah electrical subcontractor won 100% of an RM200k–300k unpaid certified progress claim, with 5% yearly interest and all adjudication costs.

In short. An electrical subcontractor in Kedah claimed the RM200k–300k unpaid balance of an interim payment certificate under CIPAA 2012, nearly three years after it was issued. The main contractor served no payment response or adjudication response. The adjudicator awarded 100% of the claim, 5% yearly interest and all adjudication costs.

At a glance

TradeElectrical works (domestic subcontractor)
MCS acted forClaimant (electrical subcontractor)
RespondentMain contractor
Contract formLetter of award (domestic subcontract)
StateKedah
Year of decision2022
Subcontract sumRM1.5m–2m
Certified work done (incl. variations)RM300k–400k
ClaimRM200k–300k (unpaid balance of an interim payment certificate)
Outcome100% of the claim
Interest5% a year on the adjudicated amount, from the notice of adjudication until full payment
CostsRespondent to bear 100% of the adjudication costs (under RM100k), including party-and-party costs

Background

The claimant is an electrical works firm. In the second quarter of 2018 a main contractor appointed it, by letter of award, as the domestic subcontractor for the electrical works on a landed housing development in Kedah. The subcontract sum was RM1.5m–2m.

The work was valued through interim payment certificates. By the third quarter of 2019 the certified cumulative work done, including variations, stood at RM300k–400k. Against that, the main contractor had paid under RM100k, and the claimant accepted a small agreed set-off for a deduction notice and returned materials. That left RM200k–300k unpaid on the certificate.

In mid-2020 the main contractor sent the claimant a settlement proposal. It offered to pay the outstanding balance in instalments over 24 months. The balance in the proposal matched the balance in the certificate. The money still did not come.

The dispute

In the second quarter of 2022, nearly three years after the certificate, the claimant served a payment claim under CIPAA 2012 for the unpaid balance. The main contractor did not serve a payment response.

The claimant served a notice of adjudication in the third quarter of 2022. The parties did not agree on an adjudicator, so the claimant asked the Director of the AIAC to appoint one. The main contractor did not answer the adjudicator's proposals on fees and service by email, so the AIAC standard terms and the default service rules in section 38 of CIPAA applied.

The claimant filed its adjudication claim for RM200k–300k, interest and costs. No adjudication response was filed. There was no hearing or site visit. The claim was decided on the documents.

Key issues and how they were argued

With no payment response, the only issue was whether the main contractor was liable to pay for the work done in the certificate, and how much.

Which certificate? A point of form could have caused trouble. The payment claim referred to the certificate as IPC No. 9. In the adjudication claim, the claimant explained that two certificates had been numbered IPC No. 8, and that it relied on the later one, issued in the third quarter of 2019. The adjudicator compared them. The date, the amount and the work done were identical. He held that the certificate in the payment claim and the one in the adjudication claim were the same document, despite the different numbering, and went on to decide liability and quantum.

Quantum. The claimant set out the arithmetic openly: certified cumulative work done, less payments received, less the agreed set-off. Admitting the payments and the set-off up front made the balance easy to check.

The settlement proposal. The claimant exhibited the main contractor's own mid-2020 settlement proposal. Because the outstanding balance in that proposal matched the certificate, the adjudicator found that the main contractor did not dispute either liability or quantum.

The decision

The adjudicator found the claim proven on the balance of probabilities. In the fourth quarter of 2022 he ordered the main contractor to pay:

  • 100% of the RM200k–300k claimed for the certified work done;
  • interest at 5% a year on the adjudicated amount, under section 25(o) of CIPAA, from the date of the notice of adjudication until full payment;
  • all of the adjudication costs, under RM100k, covering the adjudicator's fees, the AIAC's fees, the claimant's consultancy disbursement and party-and-party costs. Under section 18 of CIPAA, the adjudicator ordered costs to follow the event.

Payment was ordered within 21 calendar days of the decision.

Every case turns on its own facts and documents; past outcomes do not guarantee a similar result. This is not legal advice.

Lessons for contractors

  1. 1An old certificate can still be claimed. The certificate was nearly three years old when the payment claim was served. It was still recovered in full.
  2. 2Get the certificate reference right. Quote the same certificate number and date in the payment claim and the adjudication claim. Where the numbering is confused, explain it clearly. Here that explanation, plus identical dates and amounts, kept the claim alive.
  3. 3Keep the other side's settlement proposals. A written offer to pay the same balance in instalments was treated as showing that the debt was not disputed.
  4. 4Show your own deductions. Admitting payments and agreed set-offs makes your figure credible and leaves little to argue about.
  5. 5Silence does not stop the process. With no payment response and no adjudication response, the claim was decided on the claimant's documents.

The certified balance was recovered through a CIPAA payment claim. Turning a decision into payment is covered under enforcing an adjudication decision. For another subcontractor that recovered a certified sum in full, see the M&E retention case.

This case study is anonymised. Names, project details and exact figures have been removed or rounded. Shared with the client's consent.

FAQs

Can I still make a CIPAA claim on an interim certificate issued years ago?
In this case, yes. The certificate was issued in the third quarter of 2019 and the payment claim was served in the second quarter of 2022. With no payment response or adjudication response, the adjudicator awarded 100% of the certified balance, plus interest and costs.
What if my payment claim gives the wrong IPC number?
Here, the payment claim called the certificate IPC No. 9, while the adjudication claim relied on IPC No. 8 of the same date. The claimant explained that two certificates carried the number 8. Because the date, amount and work done were identical, the adjudicator treated them as the same certificate and decided the claim.
Does a settlement proposal help prove the debt in a CIPAA claim?
In this decision, it did. The main contractor had proposed paying the outstanding balance in instalments over 24 months, and that balance matched the certificate. The adjudicator relied on it to find that the main contractor did not dispute liability or quantum.